Three steps for installtion of HAS Hotlink Automatic Splice 

Step 1: Preparation  

Measure the conductor for full insertion one half the length of HAS and indicate with tape or mark pen Wire brush the end section thoroughly with a bristle wire brush

Step 2: Installation 

Insert conductor into splice with a smooth straight thrust through the jaws until conductor hits center stop.Do not push conductor partially in and do not twist.  

Step 3:inspection 

Before release blocks, apply a momentary "hand set" tension to make sure proper jaw gripping It is normal the conductor will move 1/4 to 1/2 inch out 

due to the sliding action of grippled jaws while tension is applied. 